Use of
directional relays
Tripping of ICTs changes power
flows for either side of network drastically and thereby may lead tripping of
other network elements too. To avoid such wide spread network disturbance it is
utmost necessary that HV backup relays shall respond only for fault on IV bus
and vice a versa. Thus ICTs HV and IV
backup relays are directional.
As discussed previously about MTA
for directional relays of EHV lines same values shall be adopted for MTA for
directional relays for ICTs. That means for overcurrent relay MTA shall be +450
(45 degree leading) and for earthfault relay it shall be -450 (45
degree lagging).
PSM
Setting IV Side
Generally power flow through ICTs
is from HV side to IV side and as directional relays are provided for ICTs in
grid; IV side overcurrent relay will not respond for overload condition on
ICTs; still IV side overcurrent PSM shall be according to ICT full load. This
is only to ensure its non-operation on load whenever there is accidental change
in power flow direction due to grid disturbance.
PSM
Setting HV Side
ICTs tap winding is designed on IV
side. Hence its HV side current for maximum capacity utilization is constant
irrespective of tap position. Hence its HV over current PSM can be decided from
ICTs rated current only irrespective of tap position.
As HV side current does not depends
upon tap position; Alarm and Load trimming scheme shall be implemented using HV
side CTs of ICTs. Hence while calculating HV side relay PSM; alarm and load
trimming scheme provided for ICT needs to be considered.
For E/F relay PSM shall be selected
as 20% or 30% depending upon expected earth fault current.
TMS
setting-Time gradation
HV side backup relay of ICTs
Protects the ICT against IV side bus faults or un-cleared fault on IV side EHV
feeders. These EHV feeders are having distance protection as its main protection.
We have adopted Zone-II time delay for distance relays as 350 ms. Hence if TMS
of the backup relays is such that the HV side relay operation time shall be 500
ms for fault on IV bus it will provide sufficient time grading between EHV
feeder Z-II and ICT HV side relay operation.
By the same logic IV side backup
relay time of operation shall also be 500 ms for considering fault on HV bus.
The setting methodology can be best understood with
the help of example.
Use of Definite Time Delay (
Highset ) Setting
We may use the vast magnitude
difference between fault current measured by backup relay of ICT during through
fault and fault in differential zone to set definite time delay (Highset)
operating characteristics of the ICT backup relay.
At 220 KV Paranda substation, it is general practice to charge 220/132 KV ICT from 132 KV side (132 KV Kurudwadi source), in the event of non availability of 220 KV source. That is sometimes 220/132 KV ICT used as a step up transformer
ReplyDeleteWhether this is going to change setting methodology by any way?
Delete