RF1: Transformer O/C E/F Settings Basic Knowledge.

Rapidfire-For Xmr Overcurrent Relay
Q1.) Setting methodology for T/F HV side O/C E/F relay is -
Depends upon voltage level
Depends upon T/F operational mode
Same irrespective of T/F operational mode
None from this
Q2.) For transformer; setting of Overcurrent PSM shall be very precise -
A) For fully loaded transformers
B) For T/f having load trimming
C) For every transformer
D) For option A or B
Q3.) TMS for HV side overcurrent relay shall be such that HV side relay operational time would be 500 ms for relay current corresponding to -
70% of LV side bus fault
LV side bus fault
TF HV Terminal Fault
None of this
Q4.) Time discrimination between HV and LV side overcurrent relay at the fault level lower than considered for TMS calculations will be -
Less
More
Depends on Source Impedance
Depends on T/F Reactance
Q5.) For T/F LV Side Non-Directional relay TMS shall be calculated considering relay current corresponding to -
A) 70% of LV Bus fault
B) LV Bus fault
C) 70% of LV Bus fault with correct use of HS
D) A or B as per use of HS
Q6.) For transformer operating in parallel; most prefered protection scheme for LV side is -
Use of only directional relay
Dual directional relay
Use of Non-directional relay
Combination of directional and non-directional elements
Q7.) Whether it is possible to operate transformer in paralle if only Non-Directional relays are available to its LV side-
YES
NO
As a compromise for rear faults
As a compromise
Q8.) For T/F LV Side Forward-Directional element considering relay current corresponding to T/F LV LA fault we need to calculate -
E/F PSM
O/C and E/F TMS
E/F HS
O/C and E/F HS
Q9.) Approximate relay setting calculations may be risky decision in case of -
A) Remote Sub-stations
B) Sub-stations close to major grid source
C) Equally in both case A or B
Always
Q10.) For T/F HV O/C E/F relay HS shall corresponding to relay current for -
T/F HV terminal fault
70% of T/F HV terminal fault
T/F LV Bus Fault
70% of T/F LV Bus Fault
Topic SETOCTF Ex-1 Your score is:
Select Zone:
Select Unit:
Code Number:

2 comments:

  1. Sir, please add Project Testing Unit, Latur

    ReplyDelete
  2. All such requests shall be considered collectively

    ReplyDelete